Call to Order
Action Items
Changes will be presented to City Council on October 17 to set a Public Hearing date of November 7, 2022. The changes will be effective January 1, 2023.
Information Items
Distributed by mail the week of September 26th.
This will be distributed at the meeting.
1. Lynden Community Center Facility Structural & Mechanical Repairs $300,000
2. Jim Kaemingk, Sr. Trail Connector: Depot Road to 8th Street $500,000
3. Grover Street Pavement Preservation $500,000
4. South Park Water, Street and Sidewalk Improvements $387,500 Grant / $562,500 Loan
Pepin Creek Main Street Bridge - Interwest - Local street traffic counts are being provided to the Police Department.
West Front Street Improvements - Stremler - Started the week of September 26th. Final paving to occur Spring, 2023.
West Front Street Culvert Replacement - Not demolishing in 2022, but will monitor closely during storm events and close road as necessary.
West Main Street - CERB application submitted, tentative ground breaking for Alliance Freeze Dry October 21nd. Potential presentation to CERB Board November 17th.
Industrial Condensate Outfall - Strider - Ribbon Cutting Date?
Bender Road Waterline - Northern - Still finalizing documentation prior to issuing Notice to Proceed.
South 6th Street CIPP - Iron Horse - Starting mid-November.
8th Street Stormwater LID - Public Open House September 29th - feedback.
Guide Meridian Pump Station - Colacurcio - Started week of September 26th.
Greenfield Pond Maintenance - Stremler - Started week of September 26th.
Kamm Road Development Work - DeKoster - Development agreement for credit toward water connection and traffic impact fees.
Mouw Ditch Bertrand Water Improvement District Meeting - held September 15th with property owners in attendance (future CERB funding).
New Business
Adjournment
Next Meeting: November 9, 2022