Bi-weekly check-in Update (we look to be on schedule)
- Benson Park
Draft of Master Plan received from SCJ Alliance with more phasing and pricing elements coming yet in January
Bridge “pre-drilling” and windmill renovation update
- Schoolyard
Sign with a copy of the approved plan in concept has been installed on site
Fence and Backstop Removal moving along well to date
- Berthusen Park
Gate is in planning with electrician and Gateway Controls
- Trails
Preliminary numbers and phased approach have been presented
- Used pickup has been purchased and is in the fleet
- Additional Parks Maintenance Employee offer letter has been sent
- IT is making adjustments to our server and training is being scheduled for use this spring